Dam

We were mandated by the Comisión Federal de Electricidad to construct a double-curvature arch dam measuring 207 metres high and 115 metres long at the ridge. This project included a diversion tunnel, a spillway tunnel capable of evacuating 3,000 m3/s, 2 tunnels (618 m long), a water intake, 21 kilometres of concrete-lined intake gallery, a surge chamber, a sloped penstock pipe and an underground plant equipped with two 146-megawatt turbines.

Background

The Zimapán hydroelectric facility is located 245 kilometres north of Mexico City on the border of the states of Queretaro and Hidalgo, at the junction of the San Juan and Tula rivers.
At this 22-kilometre long site, we constructed a dam measuring 203 metres high, with 28 kilometres of tunnel, a surge chamber, an underground plant, and access roads.
The goal of this dam is to provide electricity, and the installed capacity of 282 megawatts allows it to produce 1,292 gigawatts/hr on an annual basis.

TECHNIQUE

The characteristic feature of this project was that it was an excavation site. Excavated using traditional methods (hammer, blasting, excavators), the project includes 4.3 million m3 of excavation for only 600,000 m3 of concrete.
Sealing was ensured by building a waterproof layer on each side of the dam, and below the level of the riverbed. The sealing layer was implemented with a set of deep drilling operations on surfaces running from the dam crest to 60 or 70 metres below the riverbed.
Boreholes measuring 2 inches in diameter were made from a series of tunnels 3 metres in diameter that also served as access tunnels for machinery and workers. The holes were close enough to one another so that a cement slurry could be injected afterwards to seal up the cracks and fissures (slurry pressure-injected). Beforehand, rock permeability tests had been conducted and others were periodically redone as the injections progressed. The design of the waterproof layer for the Zimapán dam consists of two open arms over 100 metres wide on each side of the dam.
Thanks to the vertical and radial boreholes, the injections joined to form a membrane from the surface. Four levels of access tunnels were built for the injections and drainage, because the evacuation of water reaching the membrane had to be planned for in order to avoid pressure being applied to the waterproof layer. Lastly, the worksite was protected by an upstream earth and rockfill cofferdam measuring 25 metres high and a downstream cofferdam 18 metres high.

The dam located in the El-infiernillo gorge is a double-curvature arch dam. It has the particularity of being located in a gorge spanning 40 metres at the bottom, more than 400 metres in depth. As a result, this highly singular construction comprises 3 pads, including 2 support pads at 152 metres high and 5 pads on the upper section.

IMPACT

Hydroelectric power is the world’s third-leading source of electricity production, with about 16% of the electrical energy share.
This energy source provides renewable electrical power. It results from the conversion of hydraulic energy into electricity. The energy generated by the flow of water is transformed into mechanical energy by a hydraulic turbine, which is then transformed into electrical power by a synchronous generator.
This construction allows the municipality of Zimapán to produce renewable energy, with a low greenhouse gas emission level, and low operating costs.
This project is part of a long history of recognised expertise for VINCI Construction Grands Projets, in the construction of hydraulic infrastructure, including the Xiaolangdi Dam, the new Assiut Dam and the Naga Hammadi Dam.

Project participants

Client
Comisión Federal de Electricidad

Project management
Dirac

Key figures

Implementation dates
September 1990 to November 1994

Earthworks
4.3 million m3

Concrete
524,280 m3

Annual power
1,300 GWh